Proposed Site Clearance, Earthworks and Substructure Works Comprising:

  • Site clearance and earthworks
  • Piling, pile cap and stump works
  • Supporting development phases including:
    • Phase 2:
      • 2 blocks of 3-storey apartments (40 residential units)
      • 1 unit refuse chamber
    • Phase 3:
      • Block A: 23-storey apartment (264 units)
      • 5-storey car park podium with resident facilities
      • 1 unit refuse chamber

On Lot 182455 (formerly Lot 192018), Jalan Bayu Puteri 2, Taman Bayu Puteri, Mukim Plentong, Daerah Johor Bahru, Johor Darul Ta’zim.

Client / Owner

MLK TEGUH SDN BHD

Main Contractor

Contract Period

01.10.2025 – 30.06.2026

QLASSIC AWARD

Progress

99.8%

CPC

CFO

CCC

Expected CCC